Concrete calculator.

Work out how much concrete a footing, slab, trench or set of post holes needs, in cubic metres, tonnes, ready-mix order size and bags. Metres and millimetres as it comes off a drawing, or switch to feet and inches.

What are you pouring?
Allowance for over-dig and waste
Order —m³ Net — m³ + 10% = — m³, rounded up to the nearest quarter cube (how ready-mix is sold). That is about — cubic yards.
—
Weight
— t
Ready-mix
—
Pre-mixed 25 kg bags
—
Mix on site (1 : 5, roughly C20)
— × 25 kg cement + — t ballast

Guide figures for ordering, not a structural design. Footing depth on Essex clay is set on site by building control, so measure the trench as dug. Foundations in Essex.

How to use it

Measuring up for concrete.

Slabs and bases. Length times width times thickness. A 150 mm slab is the usual for a domestic garage or shed base; 100 mm is enough for a path or a light shed on hardcore.

Strip footings and trench fill. Add up the total run of trench, including corners once. Width is the trench width, not the wall width. Depth is how much concrete goes in, which for trench fill is nearly the whole trench and for a strip footing is often 300 mm or so with blockwork above. On shrinkable clay the inspector may deepen the trench on the day, so measure again before you order.

Post holes and piles. Diameter and depth of each hole, times how many. The calculator does the circle maths for you.

Waste. Nobody digs a perfect trench. Ten percent is the normal allowance and a mixer that leaves with half a cube still in the drum is cheaper than a second delivery.

FAQs

Concrete questions we get asked.

How much concrete do I need for a strip footing?

Multiply the total trench length by its width and depth in metres. A 12 m run of footing 600 mm wide and 1 m deep is 12 × 0.6 × 1.0 = 7.2 m³. Add about 10% for over-dig and waste, so order 8 m³.

What strength of concrete should I use?

For blinding and fence posts, GEN1 is fine. For house and extension footings, most Essex building inspectors expect GEN3 or C20 equivalent unless the engineer says otherwise. Slabs that take cars want C25 or C30. If in doubt, ask the inspector before you order — it costs nothing and saves a rejected pour.

Ready-mix or bags?

Above about half a cubic metre, ready-mix is cheaper, quicker and more consistent. A cubic metre is roughly 90 bags of pre-mixed 25 kg concrete, which is a lot of lifting. Below that, bags or mixing on site makes sense.

How much does a cubic metre of concrete weigh?

About 2.4 tonnes. That matters for what a barrow, a dumper or a pump can move, and for whether the ground will take a mixer truck.

Do I add extra for waste?

Yes. Trenches are never dug to exact size, ground moves, and a pour that comes up short is expensive. 10% is the usual allowance; 5% for a shuttered slab you have measured precisely.

Need hardcore or sand as well? Aggregate calculator →

Need groundworks in Essex? Get a fixed quote today.

Send a quick note and we'll come back the same working day — or call directly for an immediate response.

  • Fully insured
  • Licensed waste carrier
  • Callback within the working day
  • No obligation
WhatsApp 07495 969 705